Integral Aluminum Alloy Formwork Process Overview

Release date:2018-04-16 The author: Click on:

1. Integral aluminum alloy formwork is a system formwork


The so-called system template process is to design, use, and standardize the templates used in the construction project before the construction of the project. The work plan of the formwork system is designed and designed according to the template required in the work plan. After a rigorous manufacturing process, it is sent to the production site, and a simple assembly method is used to complete the assembly process at the site.


铝合金模板


2. Integral aluminum alloy formwork system composition: formwork system; support system; fastening system; attachment system


The formwork system constitutes the closed surface required for the construction of the concrete structure, ensuring that when the concrete is poured, the building structure is formed; the attachment system is a connection member of the formwork, so that the single piece formwork is linked into a system to form a whole; the support system supports during the construction of the concrete structure. Function, to ensure the stability of the floor, beam bottom and cantilever structure; fastening system is to ensure that the template forming plate forming the structure of the width of the size, in the casting process does not produce deformation, the template does not appear to increase mold, mold explosion phenomenon.


3. Integral aluminum alloy template operation flow


On the first day, the line was measured, the steel bar was reinforced, and the water and electricity reserve was completed.


The next day, 7:00-12:00, remove the wallboard and pass it to the upper floor to install the wall column template.


The next day Demolition layer beam template, spread to the upper installation


On the fourth day, tie beam reinforcements, support special-shaped cantilever members, and adjust and reinforce the wall posts.


On the fourth day, the steel bars of the floor boards are tied and intercalated to prepare the ground for the reserved hydropower.


Day 5 15:00-17:00 Floor Cleanup, Review Size, Concrete Preparation


Day 5 17:00-23:00 Concrete Pouring


The sixth day of the 8:00 measurement line